top of page

2013 TE SIDEWALK PROJECT

 

 

 

PROJECT FUNDING:   Grant and Local Funding

 

GRANT SOURCE:  2013 Transportation Enhancement Program  (TE)

 

ADMINISTERING AGENCY:  Alabama Department of Transportation

 

DATE OF NOTIFICATION OF AWARD:  July  2013

 

SCOPE OF PROJECT:  Streetscape Improvements 

 

LOCATION OF PROJECT:  East side of Town Avenue from South Academy Street to South Commerce Street

 

BUDGET INFORMATION:   

 

                                      Total Cost  $178,158.40

                                       

                                      Grant Funds  $130,080.00

                                      Local Funds  $  48,078.40

 

CURRENT PROJECT STATUS:   Project Complete - Awaiting Final Inspection

 

 

 

bottom of page